HSE recorded losses in 2018 – Slovenia, 12 June 2019

Slovenian HSE Group recorded a net loss in the amount of 11.8 million euros in 2018, compared to a profit of 8.2 million euros in the previous year, mostly due to the impairment of thermal power plant Sostanj assets. Without the impairment, the Group would have recorded a net profit of 6.7 million e Full […]

TES6 back in operation – Slovenia, 06 May 2019

Slovenian HSE, a company which operates thermal power plant Sostanj (TES), announced that unit 6 of the plant was successfully put back online following the maintenance carried out between 23 April and 6 May. The maintenance works included inspections of the equipment, cleaning of the flue gas an Full article available for subscribers of Energy […]

TES 6 offline until 6 May – Slovenia, 24 April 2019

Slovenian HSE, a company which operates thermal power plant Sostanj (TES), announced that on 23 April, unit 6 at the plant was shut down after 77 days of uninterrupted operation. During the planned shutdown, which should last until 6 May, inspections of equipment, cleaning of the LUVO heater gas Full article available for subscribers of […]