Overhaul of HPP Perucica completed – Montenegro, 30 August 2017

Montenegrin power utility EPCG announced that it has completed regular overhaul of its hydropower plant Perucica. According to the statement from the company, filling of the accumulation with water will be completed on 1 September, after which the plant will be put back into operation. The regular annual overhaul of HPP Perucica started on 31 […]

Annual overhaul of HPP Perucica started – Montenegro, 31 July 2017

The regular annual overhaul of hydropower plant Perucica started on 31 July. According to already established plans, all the works should be completed by 30 August 2017. As a part of this year’s overhaul of HPP Perucica regular maintenance works will be performed on the plant itself and adjacent facilities, as well as on the […]

HPP Perucica back online on 7 September – Montenegro, 3 September 2016

Montenegrin power utility EPCG announced that hydropower plant Perucica will be back online on 7 September following a regular overhaul which started on 8 August. The filling of HPP Perucica water system will start on 5 September, which includes filling of the reservoir, channels and tunnels, followed by the filling of the pipelines and testing […]